YACHT REFIT ASIA

Case studies

Superyacht refit case studies

Yacht Refit Asia manages these refits for owners. The cards are grouped as coatings work outside Thailand, yacht refit in Thailand, and refit work elsewhere in Asia. Each card shows the place. A yard is named only when it is Yacht Refit Asia's own base at Ocean Marina, or Bangkok Dock as a project site. The products those cards name are collected on the refit products and systems page.

Coatings on these programmes are carried out with our sister company Superyacht Painters, under the same founder and ownership. Where a card covers fairing, a full repaint, composite repair, or the choice of Awlgrip or Alexseal, those notes are on the Superyacht Painters site.

In progress

Two programmes are in progress. First, a 76.6 m explorer yacht refit in Singapore. Second, three 33 m newbuilds in Haiphong, Vietnam. The same cards are first in their categories below.

In progress

76.6 m explorer yacht

Hull fairing on a 76.6 m explorer yacht in Singapore
Vessel76.6 m explorer yacht
LocationSingapore
WhenDelivery April 2027
ScopeHull and superstructure refit in Singapore. Awlgrip finish. Fairing is nearly complete and the project is running ahead of schedule.

Design & planning

The programme is specified as a hull and superstructure refit. Delivery is April 2027.

Materials & systems

The published finish is Awlgrip. No other coating is named on this programme.

Process

Fairing and the Awlgrip finish are scheduled with quality inspections and sign-off against the specification. Fairing is nearly complete, and the project is running ahead of schedule.

Result

In progress. Delivery is April 2027.

See the painting side of this job on Superyacht Painters

In progress

3 × 33 m newbuilds

Site container beside three 33 m newbuilds in Haiphong, Vietnam
VesselThree 33 m newbuilds
LocationHaiphong, Vietnam
WhenHull 1 started 24 June 2026
ScopeFairing and an Alexseal finish, under climate-controlled tenting.

Design & planning

The programme is specified for fairing and the finish, under climate-controlled tenting. Hull 1 is the published start of the three 33 m newbuilds, in Haiphong, Vietnam.

Materials & systems

The finish on this card is Alexseal. The work is under climate-controlled tenting.

Process

Fairing and the Alexseal finish are scheduled under the tenting, with quality inspections and sign-off against the specification. Hull 1 started on 24 June 2026.

Result

In progress. Hull 1 started on 24 June 2026 in Haiphong, Vietnam.

See the painting side of this job on Superyacht Painters

Coatings outside Thailand

Paint-led programmes outside Thailand: a Hempel subcontract in South Korea, and coating consultancy in the United Arab Emirates. Paint carried out in Thailand stays in the next section.

40 m aluminium motor yacht

40 m aluminium motor yacht in South Korea
Vessel40 m aluminium motor yacht
LocationSouth Korea
ScopeHempel subcontract of about eight months.
StatusDelivered

Design & planning

The programme is specified as a Hempel subcontract on a 40 m aluminium newbuild. The published duration is about eight months. The work was in South Korea.

Materials & systems

The published coating is Hempel. No other brand is named.

Process

The subcontract is scheduled across the published period, with quality inspections and sign-off against the Hempel specification.

Result

Delivered. The published result is the Hempel subcontract of about eight months.

60 m motor yacht

Vessel60 m motor yacht
LocationUnited Arab Emirates
ScopeCoating consultancy and survey.
StatusDelivered

Design & planning

The programme is a coating consultancy and survey, specified as advice on a 60 m motor yacht. The work was in the United Arab Emirates.

Materials & systems

The programme is a coating consultancy and survey.

Process

The survey and the written advice are the programme. The stated work is consultancy, followed by sign-off of that advice.

Result

Delivered. The published result is the coating consultancy and survey.

50 m motor yacht

Vessel50 m motor yacht
LocationUnited Arab Emirates
ScopeCoating adviser.
StatusDelivered

Design & planning

The programme is specified as a coating adviser role on a 50 m motor yacht. The work was in the United Arab Emirates.

Materials & systems

The programme is a coating adviser role.

Process

The advice is given against a written brief, reviewed and signed off as consultancy.

Result

Delivered. The published result is the coating adviser role.

Which paint-led programmes sit outside Thailand?

A Hempel subcontract in South Korea, and coating consultancy for a 60 m motor yacht and a 50 m motor yacht in the United Arab Emirates.

Where is paint work in Thailand listed?

Paint carried out at Ocean Marina, in Phuket, or elsewhere in Thailand is in the Yacht Refit Thailand section, with the rest of that programme.

Yacht Refit Thailand

Refit programmes in Thailand. Work at Yacht Refit Asia's own base is listed as Ocean Marina, Thailand. Work at Bangkok Dock is listed as Bangkok Dock, Thailand. The Princess programmes are listed as Phuket, Thailand, including interior and upholstery refit, and paint where the specification calls for it.

40.2 m Benetti

40.2 m Benetti alongside at Ocean Marina, Thailand
Vessel40.2 m Benetti
LocationOcean Marina, Thailand
When2022–23, 12 weeks
ScopeFull exterior refinish and repairs in Awlcraft 3000.
StatusDelivered

Design & planning

The programme starts from a condition survey and a written specification of the exterior refinish and repairs. The published programme is 12 weeks in 2022–23, at Ocean Marina, Thailand, and the schedule is set from that specification.

Materials & systems

The coating on this card is Awlcraft 3000, used for the full exterior refinish and the repairs.

Process

Yacht Refit Asia runs the refinish as one programme: the specification, the schedule, quality inspections at each stage, and sign-off against the written scope. The exterior repairs stay on that sequence through the published 12 weeks.

Result

Delivered in 2022–23. The completed scope is the full exterior refinish and repairs in Awlcraft 3000 at Ocean Marina, Thailand.

41 m motor yacht

41 m motor yacht paint repairs at Ocean Marina, Thailand
Vessel41 m motor yacht
LocationOcean Marina, Thailand
ScopeAwlcraft 3000 is specified for the repairs, with a metallic blend on the repaired areas.
StatusDelivered
41 m motor yacht coating detail at Ocean Marina, Thailand

Design & planning

Planning starts from a survey. The written scope is repairs, not a full refinish. The work was at Ocean Marina, Thailand.

Materials & systems

Awlcraft 3000 is the coating named for these repairs, including a metallic blend. No other coating is named.

Process

The repairs are scheduled from the specification. Quality inspections check the blend against the surrounding finish, and the programme is signed off against that scope.

Result

Delivered at Ocean Marina, Thailand. Sign-off covered the specified Awlcraft 3000 repairs and the metallic blend.

See the painting side of this job on Superyacht Painters

60 m Oceanco

60 m Oceanco in dry dock at Bangkok Dock, Thailand
Vessel60 m Oceanco
LocationBangkok Dock, Thailand
When2015
ScopeFairing and an Alexseal refinish. The managed scope also takes in brightwork, the pool, the underwater hull and the engine room.
StatusDelivered
60 m Oceanco bow in dry dock at Bangkok Dock, Thailand

Yacht painting in Thailand

Freshly painted cabin sides on a 60 m superyacht at Bangkok Dock, Thailand
Cabin side gloss finish, 60 m motor yacht, Bangkok Dock, Thailand
Mirror-gloss black yacht topsides after refit, Thailand

Design & planning

Planning starts from a condition survey. The 2015 schedule was set from the written specification, covering brightwork, the pool, the underwater hull, the engine room and the exterior. The work was at Bangkok Dock, Thailand.

Materials & systems

Alexseal is the only coating brand named on this programme.

Process

Fairing, the refinish and the stated areas are scheduled as one programme. Quality inspections and sign-off follow the specification through to completion.

Result

Delivered in 2015. Handover closed the written specification, including the fairing and the Alexseal refinish.

See the painting side of this job on Superyacht Painters

Sunseeker Manhattan 73

Sunseeker Manhattan 73 lifted at Ocean Marina, Thailand
VesselSunseeker Manhattan 73
LocationOcean Marina, Thailand
WhenDecember 2021
ScopePaint repairs first, then Awlgrip 545 epoxy primer and Awlcraft 3000 topcoats in Super Jet Black, with red style lines.
StatusDelivered
Sunseeker Manhattan 73 stern at Ocean Marina, Thailand

Design & planning

On this Sunseeker Manhattan 73 at Ocean Marina, Thailand, paint repairs were completed first. The hull colour is Super Jet Black, with red style lines.

Materials & systems

The hull was primed with Awlgrip 545 epoxy primer and finished in Awlcraft 3000 topcoats in Super Jet Black, with red style lines.

Process

Paint repairs were completed first. The hull was then primed with Awlgrip 545 epoxy primer and finished in Awlcraft 3000 topcoats.

Result

Delivered December 2021. The hull was finished in Awlcraft 3000 topcoats in Super Jet Black, with red style lines, over Awlgrip 545 epoxy primer.

Manhattan 52

Sunseeker Manhattan 52 on stands in Thailand
VesselManhattan 52
LocationThailand
When2020
ScopeComposite repairs and a black hull.
StatusDelivered

Design & planning

The programme is planned from a survey of the composite repairs and the black hull. The written specification covers that scope. The work was in Thailand.

Materials & systems

The stated work is composite repairs and a black hull.

Process

The repairs and the hull finish are scheduled from the specification, inspected, and signed off against that scope.

Result

Delivered in 2020. The published result is the composite repairs and the black hull.

42 m catamaran

42 m catamaran under sail
Vessel42 m catamaran
LocationThailand
ScopeFairing repairs and a full Awlgrip finish.
StatusDelivered
42 m catamaran with a refit frame

Design & planning

The programme is specified from a survey of the fairing repairs and the full finish. The work was in Thailand.

Materials & systems

The finish on this card is Awlgrip.

Process

Fairing repairs are scheduled ahead of the Awlgrip finish. Quality inspections come before the finish goes on, and the programme is signed off against the specification.

Result

Delivered. The published result is fairing repairs and a full Awlgrip finish in Thailand.

34 m Camper & Nicholsons

34 m Camper & Nicholsons deck
Vessel34 m Camper & Nicholsons, 1904
LocationBangkok Dock, Thailand
ScopeFairing and a full Awlgrip finish, applied by roller, brush and tip.
StatusDelivered
34 m Camper & Nicholsons stern

Design & planning

The programme is specified for a 1904 classic: fairing and a full finish, with the application method written as roller, brush and tip. The work was at Bangkok Dock, Thailand.

Materials & systems

The published finish is Awlgrip, applied by roller, brush and tip. No other coating is named.

Process

Fairing is inspected before the Awlgrip finish. Application, further quality inspections and sign-off follow the specification.

Result

Delivered. The published result is a faired hull and a full Awlgrip finish in Thailand.

34 m sailing yacht

34 m sailing yacht topsides
Vessel34 m sailing yacht
LocationThailand
ScopeThailand newbuild. Hempel system. ABS. Featured in Boat International, April 2012.
StatusDelivered
34 m sailing yacht deck hardware

Design & planning

This Thailand newbuild is planned from a written specification. The class requirement published for the yacht is ABS.

Materials & systems

The published coating is a Hempel system. ABS is the stated class notation. No other coating is named.

Process

The Hempel system is scheduled and inspected against the specification, with sign-off that includes the ABS requirement stated for this programme.

Result

Delivered. The newbuild was featured in Boat International in April 2012.

131 ft sailing yacht

131 ft sailing yacht being moved in Thailand
Vessel131 ft sailing yacht
LocationThailand
ScopeThailand newbuild.
StatusDelivered
Keel of a 131 ft sailing yacht in Thailand

Design & planning

This Thailand newbuild is planned from a written specification.

Materials & systems

The programme is recorded against the written specification.

Process

Scheduling, quality inspections and sign-off follow the specification.

Result

Delivered. The programme is recorded as a Thailand newbuild.

27.1 m motor yacht

27.1 m motor yacht in Thailand
Vessel27.1 m motor yacht
LocationThailand
ScopeFairing, paint and composite modifications.
StatusDelivered

Design & planning

The programme is specified from a survey of the fairing, the paint and the composite modifications. The work was in Thailand.

Materials & systems

The stated work is fairing, paint and composite modifications.

Process

Those three parts are scheduled from the specification, inspected, and signed off as one programme.

Result

Delivered. The published result is the fairing, paint and composite modifications.

Manhattan 64

VesselManhattan 64
LocationThailand
ScopeRefit of a Manhattan 64.
StatusDelivered

Design & planning

The programme is planned from a written specification. The work was in Thailand.

Materials & systems

The programme is recorded against the written specification.

Process

Scheduling, quality inspections and sign-off follow the specification.

Result

Delivered in Thailand.

41–63 ft catamarans

Vessel41–63 ft catamarans
LocationThailand
ScopeRefit programmes across 41–63 ft catamarans.
StatusDelivered

Design & planning

The programmes cover catamarans from 41 ft to 63 ft. Each is planned from a written specification. The work was in Thailand.

Materials & systems

Each catamaran is recorded against its written specification.

Process

Scheduling, quality inspections and sign-off follow each specification.

Result

Delivered. The programmes cover those lengths.

Princess yachts

Princess programmes from December 2020 into 2021, including the Princess P49. Where the work was interior or upholstery, that is what the card records. These cards are in Phuket, Thailand. The saloon and ceiling before and after pairs are on the interior refit page.

Princess P49

VesselPrincess P49, 15.55 m / 51 ft
LocationPhuket, Thailand
WhenDecember 2020 to March 2021
ScopeInterior refit and upholstery refit. Interior panels and the dashboard were refitted, and each panel was removed, stripped and finished in new upholstery.
StatusCompleted March 2021

Design & planning

This yacht interior refit and yacht upholstery refit in Phuket, Thailand, is specified panel by panel, including the dashboard, from a survey of the interior. The colour change is part of the written scope. The published dates are December 2020 to March 2021.

Materials & systems

Each panel was finished in new upholstery.

Process

Each panel is removed, stripped and refitted. Scheduling, quality inspections and sign-off follow that sequence through to completion.

Result

Completed in March 2021. Interior panels changed colour, each panel was refitted with new upholstery, and the dashboard was included.

Princess Y78

VesselPrincess Y78, 24.67 m
LocationPhuket, Thailand
When2021
ScopeGelcoat and veneer border repairs, interior and exterior Sikaflex renewal, and teak steps renewed in Burmese riftsawn teak.
StatusCompleted 2021

Design & planning

The programme in Phuket is specified from a survey of the gelcoat, the veneer borders, the sealant and the teak steps. The yacht is a Princess Y78, 24.67 m, and the published year is 2021.

Materials & systems

Sikaflex is the published sealant for the interior and exterior renewal. The teak steps were renewed in Burmese riftsawn teak. Gelcoat and veneer border repairs are in the scope.

Process

The repairs, the Sikaflex renewal and the teak steps are scheduled from the specification, inspected, and signed off as one programme.

Result

Completed in 2021. The published result is the gelcoat and veneer border repairs, the Sikaflex renewal, and the teak steps in Burmese riftsawn teak.

Princess 78

VesselPrincess 78
LocationPhuket, Thailand
When2021
ScopeA yacht interior refit, including floor bleaching.
StatusCompleted 2021

Design & planning

This yacht interior refit in Phuket, Thailand, is specified from a survey that includes the floors to be bleached. The published year is 2021.

Materials & systems

The stated interior work includes floor bleaching.

Process

The interior work is scheduled from the specification, inspected, and signed off against that scope.

Result

Completed in 2021. The published result is the yacht interior refit, including floor bleaching.

Princess P85

VesselPrincess P85
LocationPhuket, Thailand
WhenFebruary to June 2021
ScopeA yacht upholstery refit and yacht interior refit.
StatusCompleted June 2021

Design & planning

This yacht upholstery refit and yacht interior refit in Phuket, Thailand, is specified from a survey of the interior and the upholstery. The published dates are February to June 2021.

Materials & systems

Upholstery is part of the published scope. The upholstery product is not named, and no coating brand is published.

Process

The upholstery and interior work are scheduled across the published months, with quality inspections and sign-off against the specification.

Result

Completed in June 2021. The published result is the yacht upholstery refit and yacht interior refit.

Princess 88

VesselPrincess 88
LocationPhuket, Thailand
When2021
ScopeRefit programme recorded for 2021.
StatusCompleted 2021

Design & planning

The programme is planned from a written specification. The year is 2021, and the work was in Phuket.

Materials & systems

The programme is recorded against the written specification.

Process

Scheduling, quality inspections and sign-off follow the specification.

Result

Completed in 2021 in Phuket.

What do the Thailand cards cover?

Work at Ocean Marina, Thailand, at Bangkok Dock, Thailand, or in Phuket, Thailand. The scope can include interior and upholstery refit.

Where are the Princess programmes listed?

The Princess programmes, including the Princess P49, are in the Yacht Refit Thailand section. Those cards show Phuket, Thailand.

Yacht Refit Asia

Refit and project management beyond the Thailand cards. Singapore starts with the 76.6 m explorer yacht, then a 55 m motor yacht and a 40.8 m Benetti. Vietnam starts with the three 33 m newbuilds, then Hong Kong.

In progress

76.6 m explorer yacht

Vessel76.6 m explorer yacht
LocationSingapore
WhenDelivery April 2027
ScopeHull and superstructure refit in Singapore. Awlgrip finish. Fairing is nearly complete and the project is running ahead of schedule.

Design & planning

The programme is specified as a hull and superstructure refit. Delivery is April 2027.

Materials & systems

The published finish is Awlgrip. No other coating is named on this programme.

Process

Fairing and the Awlgrip finish are scheduled with quality inspections and sign-off against the specification. Fairing is nearly complete, and the project is running ahead of schedule.

Result

In progress. Delivery is April 2027.

See the painting side of this job on Superyacht Painters

55 m motor yacht

Vessel55 m motor yacht
LocationSingapore
When2025
ScopeRefit in Singapore, including a composite repair.
StatusDelivered

Design & planning

The programme is planned from a written specification. The published year is 2025. A composite repair is recorded.

Materials & systems

The programme includes a composite repair.

Process

The refit is scheduled from the specification, with quality inspections and sign-off against the written scope.

Result

Delivered in 2025. The published record is the refit and the composite repair.

40.8 m Benetti

Vessel40.8 m Benetti
LocationSingapore
When2025
ScopeWorks under RINA in Singapore.
StatusDelivered

Design & planning

The programme is specified with works under RINA, so the class requirement sits in the written scope. The published year is 2025.

Materials & systems

The class reference on this programme is RINA.

Process

The works are scheduled, inspected and signed off under the stated RINA scope.

Result

Delivered in 2025. The published result is the works under RINA.

In progress

3 × 33 m newbuilds

VesselThree 33 m newbuilds
LocationHaiphong, Vietnam
WhenHull 1 started 24 June 2026
ScopeFairing and an Alexseal finish, under climate-controlled tenting.

Design & planning

The programme is specified for fairing and the finish, under climate-controlled tenting. Hull 1 is the published start of the three 33 m newbuilds, in Haiphong, Vietnam.

Materials & systems

The finish on this card is Alexseal. The work is under climate-controlled tenting.

Process

Fairing and the Alexseal finish are scheduled under the tenting, with quality inspections and sign-off against the specification. Hull 1 started on 24 June 2026.

Result

In progress. Hull 1 started on 24 June 2026 in Haiphong, Vietnam.

See the painting side of this job on Superyacht Painters

33 m Ferretti Navetta

33 m Ferretti Navetta in Hong Kong
Vessel33 m Ferretti Navetta
LocationHong Kong
ScopeEmergency work on the hull and the diesel tank, in composite, with RINA approval recorded on the programme.
StatusDelivered

Design & planning

This was planned as emergency work. The specification covers the hull and the diesel tank, and RINA approval is part of that scope. The work was in Hong Kong.

Materials & systems

Composite is the material recorded for the repairs. RINA approval is recorded with that scope.

Process

The emergency scope is scheduled against the written repairs, inspected, and signed off with the stated RINA approval.

Result

Delivered in Hong Kong. Handover covered the hull work and the diesel tank, with the RINA approval recorded on the programme.

See the painting side of this job on Superyacht Painters

What does the Asia group cover?

Refit and project management in Singapore, Vietnam and Hong Kong.

Which cards are the Singapore programmes?

The 76.6 m explorer yacht, a 55 m motor yacht and a 40.8 m Benetti. The explorer is in progress.

Heritage projects

Delivered programmes in the United Kingdom and Europe, managed as refits and newbuild programmes.

  • 75 m sailing yacht

    75 m. Southampton, UK, 2005–06.

    Delivered

  • 80 m classic yacht

    80 m. Devonport, UK.

    Delivered

  • 75 m motor yacht

    75 m. Plymouth, UK.

    Delivered

  • 57 m motor yacht

    57 m. Portchester, UK.

    Delivered

  • 45.7 m motor yacht

    45.7 m. Portchester, UK.

    Delivered

  • 48.5 m motor yacht

    Rebuild and repaint at Lowestoft, UK.

    Delivered

  • 40 m sailing yacht

    Refit in Plymouth, UK.

    Delivered

  • 37 m classic yacht

    Refit in Gosport, UK.

    Delivered

  • 33 m sailing yacht

    Newbuild in Sittingbourne, Kent, UK.

    Delivered

  • 91 ft sailing yacht

    Refit in Southampton, UK.

    Delivered

  • 29 m yacht

    29 m newbuild, UK.

    Delivered

  • 26 m motor yacht

    26 m. Portchester, UK.

    Delivered

  • 42 ft yacht, 2001–2005

    Gosport, UK, including a 42 ft yacht.

    Delivered

  • Wind turbine blades

    21 × 40 m blades in Gosport, UK.

    Delivered

  • Seven 72 ft racing yachts

    Plymouth, UK.

    Delivered

  • Open 60 racing yachts

    New builds, UK.

    Delivered

  • Speed-record racing craft

    United Kingdom. The programme was managed as fairing in Hempel, specified for racing, and the weight of each product used was recorded. The published result is 65.45 knots in November 2012, the world sailing speed record.

    Delivered

  • Plug and mould work

    United Kingdom.

    Delivered

  • 95 m motor yacht

    95 m, Malta.

    Delivered

  • 72 m motor yacht

    72 m newbuild, France.

    Delivered

  • 35.5 m motor yacht

    35.5 m, Viareggio, Italy.

    Delivered

  • Racing trimaran

    Vannes, France.

    Delivered

  • America's Cup plug and moulds

    Vannes, France.

    Delivered

  • 60, 70 and 90 ft catamarans

    France.

    Delivered

  • 65 ft catamaran

    Caen, France.

    Delivered

  • Motor yacht programmes, 2007–09

    Denmark.

    Delivered

Questions

Which projects are on the case-study cards?

The countries are Singapore, Thailand and Vietnam. Three groups follow the in-progress programmes. Paint-led work outside Thailand includes the Hempel subcontract in South Korea and coating consultancy in the United Arab Emirates. The Thailand group covers work at Ocean Marina, Princess programmes in Phuket, and other programmes listed as Thailand. The Asia group covers refit and project management in Singapore, Vietnam and Hong Kong, including the 76.6 m explorer yacht, a 55 m motor yacht, a 40.8 m Benetti and three 33 m newbuilds. Delivered UK and European programmes stay in the heritage list.

Where is the existing project list?

The same programmes are on the projects page. The two in-progress programmes are listed first there as well.